In accordance with the Home Rule Charter of the City of Weatherford, the Mayor and two Council Members also serve as members on the Municipal Utility Board. No action specific to the City Council is scheduled for items discussed at this meeting; however, a quorum of the City Council will usually be present at every meeting of the Municipal Utility Board.
Consider approval of the minutes of the Municipal Utility Board meeting held May 29, 2025.
All of the Consent Agenda Items are considered to be routine and self-explanatory and will be enacted with one motion. There will be no separate consideration of these items unless the Council or Board removes the item from Consent.
Staff recommends approval.
Staff recommends authorizing the City Manager to execute a professional services contract with Kimley-Horn and Associates, Inc. for the design of the Harberger Hill Pump Station Evaluation and 7th/Franklin Street Water Improvements project in an amount not to exceed $215,000 for a total aggregate fiscal year expenditure amount of $2,136,570.
Staff recommends authorizing the City Manager to execute a construction contract with Patcon Services, LLC for the Water and Wastewater Improvements - 100-600 Block of West Columbia project in the amount not to exceed $1,165,737.49 for a total aggregate fiscal year expenditure amount of $2,961,785.
Staff recommends that the Municipal Utility Board authorize the City Manager to execute Amendment No. 2 to the Wholesale Wastewater Service Agreement with the City of Hudson Oaks.
Staff recommends that the Municipal Utility Board adopt Resolution R2025-07, authorizing the City Manager to execute a Principal Forgiveness Agreement and Escrow Agreement with the Texas Water Development Board.
Water Purification Plant Project Update
FUTURE AGENDA ITEMS